Understanding Big Shift Construction

Understanding Big Shift Construction

The Big Shift is providing the infrastructure for a more sustainable way to heat campus — a task easier said than done. Every segment requires several phases of construction, and with dozens of segments across campus, a lot of work is being done to accomplish this crucial shift to hot water-based heating. Find out about the phases of construction below.

Safety

During this phase, pedestrian and vehicular detour signage is placed and fencing is put up around the construction area.

Impact: pedestrian and vehicle detours, low noise level

Trench

During this phase, construction crews saw cut and demolish portions of the asphalt/pavement and excavate and shore trenches.

Impact: medium noise level, some saw cutting asphalt and occasional jackhammering

Pipeline Fabrication and Placement

Once trenches have been dug, it's time to place the new hot water pipes. Construction crews fuse the portions of the pipes together then place them into the trench. Pipes are also pressure testing during this phase.

Impact: medium noise level

Insulate and Backfill

After pipes have been placed and tested, construction crews place Gilsulate powder in the trenches to insulate the pipes. The trenches are then backfilled.

Impact: medium noise level

Temporary Surface Restoration

Backfilled trenches are repaved with an intermediary solution prior to final surface restoration.

Impact: medium to high noise level, occasional jackhammering

Fences come down

The bulk of construction is complete and the fences surrounding the construction area can come down.

Impact: low noise level

Final Surface Restoration

Following the main phases of construction, crews will go back to restore the affected area including a full restoration of the surface and any other impacted areas.

Impact: medium to high noise level, occasional jackhammering