Big Shift trench is excavated

Construction Schedule and Progress

Big Shift Construction Schedule and Progress

The size and scope of Big Shift construction is, appropriately, very big. To make it easier to track progress of construction and to get an idea of how construction may impact you, we've split construction into phases. 

Find out more about each construction phase, including more details on noise levels and other possible disruptions. For more detailed information about the "segments" shown below, visit our construction activity schedule.

Key: ✓ = Complete; ♦ = In Progress

 

Construction Duration*

Safety

Trench

Pipeline Fabrication and Placement

Insulate and Backfill

Surface Restoration

Fences come down

Noise level

 

Low

Medium to High

Medium to High

Medium

Medium to High

Low

Robbins & Hart Hall
segment 6.8

10/18 - 12/10/21

 

 

 

 

 

 

California Lecture Hall
segment 6.4

10/4 - 10/15/21

 

 

 

 

 

Everson Hall
segment 3.4

9/28 - 11/30/21

 

 

 

 

 

Hutchison Drive
(Art Building & Everson)
segment 3.6, 3.8

8/16 - 10/15/21

 

 

 

 

Surge III
segment 2.1

8/10 - 10/1/21

 

 

 

Hutchison Drive
(Everson Hall)
segment 3.2

7/30 - 9/30/21

 

Hutchison Drive
(between Olson Hall and Music Building)
segment 4.3

7/15 - 8/16/21

Landscape Restoration Fall 2021

 

Sciences Lecture Hall
segment 2.2

7/13 - 8/20/21

Landscape Restoration Fall 2021

East Quad
segment 4.7, 4.13

7/12 - 8/20/21

Landscape Restoration August - September 2021

Hutchison Drive
(at Student Community Center)
segment 3.1

7/10 - 7/30/21

North Quad/California Ave
segment 6.1-1

 

West Quad/Memorial Union
segment 5.5

5/10 - 6/28/21

Hutchison Drive
segment 2.5

5/10 - 6/4/21

California Ave
segment 6.9

4/21 - 6/4/21

Landscape Restoration Fall 2021

California Ave
segment 6.7

4/12 - 6/4/21

Wickson/Kerr Hall
segment 6.3

3/22 - 5/7/21

California Ave
(at Robbins Hall)
segment 6.6

3/8 - 4/19/21

Asmundson Hall
segment 6.2

3/1 - 3/26/21

Bioletti Way
(at Latitude)
segment 1.2, 1.3, 1.4

2/18 - 6/11/21

Chilled Water

(Hutchison at Learning Center)

2/1 - 5/9/21

California Ave.
(at California Hall)
segment 6.5

12/21 - 3/5/21

Silo

segment 2.4

12/10 - 1/11/21

Hardscape Restoration Fall 2021

Tercero Hall Dr.
(at Currant Hall)
segment 1.1 (See detour.)

12/7 - 4/16/21

Paving Restoration Spring 2022

Plant & Environmental Sciences and Hunt Hall

segments: 5.7, 5.8

11/13 - 3/19/21

Landscape Restoration Fall 2021

Young Hall
(along East Quad)
segment: 4.15

11/10 - 3/19/21

Hardscape Restoration August - September 2021

Hickey Gym
segment: 5.2

10/5 - 10/30/20

Landscape Restoration Fall 2021

California Ave
(near Asmundson Hall)
segment: 6.1-2

9/16 - 12/10/20

Veihmeyer Hall
segment: 5.9

9/15 - 10/30/20

Landscape Restoration Fall 2021

Young Hall
(Courtyard)
segments: 4.16, 4.17

8/31 - 11/31/20

Landscape Restoration Fall 2021

East Quad
(at Memorial Union)
segments: 4.14-1, 4.14-2

6/4 - 12/18/21

Landscape Restoration Fall 2021

North Quad
(west of West Quad)
segments: 5.6-1, 5.6-2

5/26 - 10/28/20

North Quad
(east of West Quad)
segments: 5.1, 5.3, 5.4

5/26 - 9/2/20

               

*Timeframe excludes final surface restoration.