Construction Schedule and Progress

Big Shift trench is excavated

Big Shift Construction Schedule and Progress

The size and scope of Big Shift construction is, appropriately, very big. To make it easier to track progress of construction and to get an idea of how construction may impact you, we've split construction into phases. 

Find out more about each construction phase, including more details on noise levels and other possible disruptions. For more detailed information about the "segments" shown below, visit our construction activity schedule.

Key: ✓ = Complete; ♦ = In Progress

 

Construction Duration*

Safety

Trench

Pipeline Fabrication and Placement

Insulate and Backfill

Temp. Surface Restoration

Fences come down

Final Surface Restoration

Noise level

 

Low

Medium to High

Medium to High

Medium

Medium to High

Low

Medium to High

Hickey Gym
segment: 5.2

10/5 - 10/23/20

 

 

 

 

 

 

 

Kerr Hall
(Communication line)

9/21 - 10/3/20

 

 

 

 

 

California Ave
(near Asmundson Hall)
segment: 6.1-2

9/16 - 11/9/20

 

 

 

 

Veihmeyer Hall
segment: 5.9

9/15 - 10/30/20

 

 

 

 

Young Hall
(Courtyard)
segments: 4.16, 4.17

8/31 - 10/30/20

 

 

 

 

Young Hall
(along East Quad)
segment: 4.15

8/31 - 10/30/20

 

 

 

 

 

East Quad
(at Memorial Union)
segments 4.14-1, 4.14-2

6/4 - 10/17/20

 

 

North Quad
(east of West Quad)
segments 5.1, 5.3, 5.4

5/26 - 9/2/20

TBD, 2021

North Quad
(west of West Quad)
segments 5.6-1, 5.6-2

5/26 - 10/9/20

 

TBD, 2021

                 

*Timeframe excludes final surface restoration.