Big Shift Construction Schedule and Progress
The size and scope of Big Shift construction is, appropriately, very big. To make it easier to track progress of construction and to get an idea of how construction may impact you, we've split construction into phases.
Find out more about each construction phase, including more details on noise levels and other possible disruptions. For more detailed information about the "segments" shown below, visit our construction activity schedule.
Key: ✓ = Complete; ♦ = In Progress
Construction Duration* |
|||||||
Noise level |
|
Low |
Medium to High |
Medium to High |
Medium |
Medium to High |
Low |
Bioletti Way |
2/18 - 3/19/21 |
||||||
California Ave |
2/12 - 3/19/21 |
||||||
Chilled Water (Hutchison at Learning Center) |
2/1 - 4/9/21 |
||||||
California Ave. |
12/21 - 2/12/21 |
✓ |
✓ |
✓ |
♦ |
♦ |
|
Silo segment 2.4 |
12/10 - 1/11/21 |
✓ |
✓ |
✓ |
✓ |
♦ |
✓ |
Tercero Hall Dr. |
12/7 - 2/19/21 |
✓ |
✓ |
✓ |
♦ |
♦ |
|
Plant & Environmental Sciences and Hunt Hall segments: 5.7, 5.8 |
11/13 - 2/26/21 |
✓ |
♦ |
♦ |
♦ |
♦ |
|
Young Hall (along East Quad) segment: 4.15 |
11/10 - 2/26/21 |
✓ |
✓ |
♦ |
♦ |
||
Hickey Gym |
10/5 - 10/30/20 |
✓ |
✓ |
✓ |
✓ |
Temporary Surface |
✓ |
California Ave |
9/16 - 12/10/20 |
✓ |
✓ |
✓ |
✓ |
Temporary Surface |
✓ |
Veihmeyer Hall |
9/15 - 10/30/20 |
✓ |
✓ |
✓ |
✓ |
♦ |
✓ |
Young Hall |
8/31 - 11/31/20 |
✓ |
✓ |
✓ |
✓ |
♦ |
✓ |
East Quad |
6/4 - 12/18/21 |
✓ |
✓ |
✓ |
✓ |
♦ |
✓ |
North Quad (west of West Quad) segments: 5.6-1, 5.6-2 |
5/26 - 10/28/20 |
✓ |
✓ |
✓ |
✓ |
Temporary Surface Restoration Complete (Final TBD, 2021) |
✓ |
North Quad (east of West Quad) segments: 5.1, 5.3, 5.4 |
5/26 - 9/2/20 |
✓ |
✓ |
✓ |
✓ |
Temporary Surface Restoration Complete (Final TBD, 2021) |
✓ |
*Timeframe excludes final surface restoration.