Big Shift trench is excavated

Construction Schedule and Progress

Big Shift Construction Schedule and Progress

Big Shift is taking a district-by-district approach to make the massive infrastructure change manageable. Construction for the first and biggest district, the Quad district is complete. The next district on the docket, the "Sprocket District," is in the preliminary planning stages. Once construction crews break ground, you can track progress and upcoming construction here.

Quad District

With all the pipes laid, trenches filled and sidewalks and landscapes restored the Quad District is complete! The table below shows all the work accomplished in the first district.

Key: ✓ = Complete; ♦ = In Progress

 

Construction Duration*

Safety

Trench

Pipeline Fabrication and Placement

Insulate and Backfill

Surface Restoration

Fences come down

Noise level

 

Low

Medium to High

Medium to High

Medium

Medium to High

Low

Storer Mall
segment 6.65

7/18 - 9/16/22

Dec. 2022

Chemistry
segment 3.3

5/16 - 5/31/22

Shields Library
(East side)
segment 4.1

3/14 - 5/20/22

Jan. 2023

South Hall
segment 4.9, 4.10

3/9 - 5/20/22

Voorhies Hall
segment 4.12

2/28 - 5/20/22

Shields Library
(Northeast Corner)
segment 4.6

2/7 - 3/11/22

Dutton Hall
segment 4.11

2/7 - 3/8/22

Olson Hall
segment 4.2

1/24 - 3/11/22

Shields Avenue at East Quad
segment 4.8-1, 4.8-2

 

12/13-3/4/22

Sproul Hall
segment 4.4, 4.5

11/15-1/21/22

 

 

 

 

 ✓

Robbins & Hart Hall
segment 6.8

11/11 - 1/24/22

California Lecture Hall
segment 6.4

10/4 - 10/15/21

Everson Hall
segment 3.4

9/28 - 11/30/21

Hutchison Drive
(Art Building & Everson)
segment 3.6, 3.8

8/16 - 1/28/22

Surge III
segment 2.1

8/10 - 10/1/21

Hutchison Drive
(Everson Hall)
segment 3.2

7/30 - 9/30/21

Hutchison Drive
(between Olson Hall and Music Building)
segment 4.3

7/15 - 8/16/21

Sciences Lecture Hall
segment 2.2

7/13 - 8/20/21

East Quad
segment 4.7, 4.13

7/12 - 8/20/21

Hutchison Drive
(at Student Community Center)
segment 3.1

7/10 - 7/30/21

North Quad/California Ave
segment 6.1-1

 

West Quad/Memorial Union
segment 5.5

5/10 - 6/28/21

Hutchison Drive
segment 2.5

5/10 - 6/4/21

California Ave
segment 6.9

4/21 - 6/4/21

California Ave
segment 6.7

4/12 - 6/4/21

Wickson/Kerr Hall
segment 6.3

3/22 - 5/7/21

California Ave
(at Robbins Hall)
segment 6.6

3/8 - 4/19/21

Asmundson Hall
segment 6.2

3/1 - 3/26/21

Bioletti Way
(at Latitude)
segment 1.2, 1.3, 1.4

2/18 - 6/11/21

Chilled Water

(Hutchison at Learning Center)

2/1 - 5/9/21

California Ave.
(at California Hall)
segment 6.5

12/21 - 3/5/21

Silo

segment 2.4

12/10 - 1/11/21

Tercero Hall Dr.
(at Currant Hall)
segment 1.1 (See detour.)

12/7 - 4/16/21

Plant & Environmental Sciences and Hunt Hall

segments: 5.7, 5.8

11/13 - 3/19/21

Young Hall
(along East Quad)
segment: 4.15

11/10 - 3/19/21

Hickey Gym
segment: 5.2

10/5 - 10/30/20

California Ave
(near Asmundson Hall)
segment: 6.1-2

9/16 - 12/10/20

Veihmeyer Hall
segment: 5.9

9/15 - 10/30/20

Young Hall
(Courtyard)
segments: 4.16, 4.17

8/31 - 11/31/20

East Quad
(at Memorial Union)
segments: 4.14-1, 4.14-2

6/4 - 12/18/21

North Quad
(west of West Quad)
segments: 5.6-1, 5.6-2

5/26 - 10/28/20

North Quad
(east of West Quad)
segments: 5.1, 5.3, 5.4

5/26 - 9/2/20

               

*Timeframe excludes final surface restoration.