
Quad District: May 14, 2020 Update
Construction Activity as of May 14, 2020
The biggest impact will be the closure of North Quad. Download the map.
Approximately three crews will be working during this timeframe. Crews 1 and 2 will be trenching and laying pipe and Crew 3 will be preparing to install a new heat exchanger.
May 26 - August 14, 2020 Traffic Control
Download the map showing detours, where roads are completely closed or closed to through traffic.
Crew 1 |
May 26 - August 14, 2020 |
Location: | North Quad & California Ave. Heading East |
Activity: | Trenching and excavating – Fenced area |
Noise: | Medium level, some saw cutting asphalt and occasional jackhammering |
Closures: | North Quad will be closed – some sidewalks may not passable |
Crew 2 | May 26 - August 14, 2020 |
Location: | North Quad at West Quad Heading East |
Activity: | Trenching and excavating – Fenced area |
Noise: | Medium level, some saw cutting asphalt and occasional jackhammering |
Closures: | North Quad will be closed – some sidewalks may not passable |
Crew 3 | May 26 - June 30, 2020 |
Location: | Across from Wickson Hall |
Activity: | Grading, shrub removal, land preparation for concrete slab |
Noise: | Medium level, asphalt removal noise |
Closures: | Access to Wickson and Wellman is limited from California Avenue |