May 14, 2020 Update

Image of contractor climbing out of a trench.

Construction Activity as of May 14, 2020

The biggest impact will be the closure of North Quad. Download the map. 

Approximately three crews will be working during this timeframe. Crews 1 and 2 will be trenching and laying pipe and Crew 3 will be preparing to install a new heat exchanger. 

 

Crew 1

May 26 - August 14, 2020
Location: North Quad & California Ave.  Heading East
Activity: Trenching and excavating – Fenced area
Noise: Medium level, some saw cutting asphalt and occasional jackhammering
Closures: North Quad will be closed  – some sidewalks may not passable
   
Crew 2 May 26 - August 14, 2020
Location: North Quad at West Quad Heading East
Activity: Trenching and excavating – Fenced area
Noise: Medium level, some saw cutting asphalt and occasional jackhammering
Closures: North Quad will be closed  – some sidewalks may not passable
   
Crew 3 May 26 -  June 30, 2020
Location: Across from Wickson Hall
Activity: Grading, shrub removal, land preparation for concrete slab
Noise: Medium level, asphalt removal noise
Closures: Access to Wickson and Wellman is limited from California Avenue
   

Tags