Image of contractor climbing out of a trench.

Quad District: May 14, 2020 Update

Construction Activity as of May 14, 2020

The biggest impact will be the closure of North Quad. Download the map. 

Approximately three crews will be working during this timeframe. Crews 1 and 2 will be trenching and laying pipe and Crew 3 will be preparing to install a new heat exchanger. 

 

Crew 1

May 26 - August 14, 2020
Location: North Quad & California Ave.  Heading East
Activity: Trenching and excavating – Fenced area
Noise: Medium level, some saw cutting asphalt and occasional jackhammering
Closures: North Quad will be closed  – some sidewalks may not passable
   
Crew 2 May 26 - August 14, 2020
Location: North Quad at West Quad Heading East
Activity: Trenching and excavating – Fenced area
Noise: Medium level, some saw cutting asphalt and occasional jackhammering
Closures: North Quad will be closed  – some sidewalks may not passable
   
Crew 3 May 26 -  June 30, 2020
Location: Across from Wickson Hall
Activity: Grading, shrub removal, land preparation for concrete slab
Noise: Medium level, asphalt removal noise
Closures: Access to Wickson and Wellman is limited from California Avenue
   

Tags