Construction Updates

February 12, 2021 Update

February 12, 2021

Big Shift crews are making progress across the map, backfilling trenches on California Avenue and Tercero Hall Drive and trenching on Hutchison Drive.

Detours

A portion of California Avenue from Kleiber Hall Drive to Storer Mall is closed to all traffic. There is also a closure on Hutchison Drive between Bioletti Way and California Avenue, which routes traffic through the California Avenue detours. Find more information about detours.

December 11, 2020 Update

December 10, 2020
Big Shift crews have made significant progress in construction near Young Hall and in the Young Hall courtyard and are working on finalizing construction near East Quad. In addition, crews have started construction near the Silo and on Tercero Hall Drive.

November 20, 2020 Update

November 20, 2020
Crews have started construction between the Plant & Environmental Sciences building and continue construction across the Quad District.

October 30, 2020 Update

October 30, 2020
Crews finished work on North Quad and continue construction on California Avenue, East Quad and in the Young Hall courtyard.

October 9, 2020 Update

October 09, 2020
Crews began construction near Hickey Gym and Kerr Hall and continue work on California Ave, East Quad and the Young Hall courtyard.

September 18, 2020 Update

September 18, 2020
Big Shift construction crews are hard at work, continuing construction at Young Hall, East Quad and portions of North Quad.

August 28, 2020 Update

August 28, 2020
As crews finalize work on North Quad and continue work on East Quad, Big Shift construction will be expanding off of East Quad and into the Young Hall Courtyard.

August 6, 2020 Update

August 07, 2020
Approximately four crews will be working during this timeframe. Crews 1 and 2 are installing pipe on North Quad while Crew 3 does the same on East Quad. Crew 4 is working near the Enology Lab Building on the construction of a heat exchanger building as well as nearby trenching.

July 17, 2020 Update

July 17, 2020
North Quad and East Quad near Memorial Union continue to see closures as crews install pipeline near, place insulation and backfill the area.

June 26, 2020 Update

June 25, 2020
Construction crews continue trenching, excavating, and installing pipe near the Memorial Union along North Quad and now stretching down East Quad, resulting in closures and detours.