June 5, 2020 Update

Big Shift construction

Construction Activity as of June 5, 2020

The biggest impact will be the closure of North Quad. Download the map. 

Approximately three crews will be working during this timeframe. Crews 1 and 2 have begun trenching and laying pipe while Crew 3 is preparing to install a new heat exchanger.

Edited June 5 to reflect updated date ranges for Crews 1 and 2 and work being done by Crew 3.

Crew 1

June 8 - July 30, 2020
Location: North Quad & California Ave.  Heading East
Activity: Trenching and excavating – Fenced area
Noise: Medium level, some saw cutting asphalt and occasional jackhammering
Closures: North Quad will be closed  – some sidewalks may not passable
   
Crew 2 June 8 - August 14, 2020
Location: North Quad at West Quad Heading East
Activity: Trenching and excavating – Fenced area
Noise: Medium level, some saw cutting asphalt and occasional jackhammering
Closures: North Quad will be closed  – some sidewalks may not passable
   
Crew 3 June 4 -  August 3, 2020
Location: Across from Memorial Union
Activity: Grading, shrub removal, land preparation for concrete slab
Noise: Medium level, asphalt removal noise
Closures: Access to Memorial Union is limited from East Quad
   

Tags