Quad District: June 26, 2020 Update
Construction Activity as of June 26, 2020
The biggest impact will be the closure of North Quad. Download the map.
Approximately four crews will be working during this timeframe. Crews 1 and 2 are trenching, excavating and installing pipe on North Quad while Crew 3 does the same on East Quad. Crew 4 is working near the Enology Lab Building on the construction of a heat exchanger building as well as nearby trenching.
May 26 - August 14, 2020 Traffic Control
Download the map showing detours, where roads are completely closed or closed to through traffic. Updated for clarity on June 5.
Crew 1 | June 8 - July 30, 2020 |
Location: | North Quad & California Ave. Heading East |
Activity: | Trenching, excavating, pipe line installation, placement of Gilsulate insulation and backfilling – Fenced area |
Noise: | Medium level, occasional jackhammering |
Closures: | North Quad will be closed |
Crew 2 | June 8 - August 14, 2020 |
Location: | North Quad at West Quad Heading East |
Activity: | Trenching, excavating, pipe line installation, placement of Gilsulate insulation and backfilling – Fenced area |
Noise: | Medium level, occasional jackhammering |
Closures: | North Quad will be closed – some sidewalks may not passable |
Crew 3 | June 4 - August 3, 2020 |
Location: | East Quad at Memorial Union |
Activity: | Trenching, excavating pipe line installation, placement of Gilsulate insulation and back filling - Fenced area |
Noise: | Medium level, occasional jackhammering |
Closures: | Access to Memorial Union is limited from East Quad |
Crew 4 | May 26 - November 30, 2020 |
Location: | West of Enology Building |
Activity: | Construction of Enology Heat Exchanger Building - Trenching, excavating, underground pipe installation - Fenced area |
Noise: | Medium level, occasional jackhammering |
Closures: | None |