Man standing by a machine fusing two sections of pipe together
Sections of the new hot water pipe are fused together to create the length we need before being installed.

Quad District: June 26, 2020 Update

Construction Activity as of June 26, 2020

The biggest impact will be the closure of North Quad. Download the map

Approximately four crews will be working during this timeframe. Crews 1 and 2 are trenching, excavating and installing pipe on North Quad while Crew 3 does the same on East Quad. Crew 4 is working near the Enology Lab Building on the construction of a heat exchanger building as well as nearby trenching.

 

Crew 1 June 8 - July 30, 2020
Location: North Quad & California Ave.  Heading East
Activity: Trenching, excavating, pipe line installation, placement of Gilsulate insulation and backfilling – Fenced area
Noise: Medium level, occasional jackhammering
Closures: North Quad will be closed
   
Crew 2 June 8 - August 14, 2020
Location: North Quad at West Quad Heading East
Activity: Trenching, excavating, pipe line installation, placement of Gilsulate insulation and backfilling – Fenced area
Noise: Medium level, occasional jackhammering
Closures: North Quad will be closed  – some sidewalks may not passable
   
Crew 3 June 4 -  August 3, 2020
Location: East Quad at Memorial Union
Activity: Trenching, excavating pipe line installation, placement of Gilsulate insulation and back filling - Fenced area
Noise: Medium level, occasional jackhammering
Closures: Access to Memorial Union is limited from East Quad
   
Crew 4 May 26 - November 30, 2020
Location: West of Enology Building
Activity: Construction of Enology Heat Exchanger Building - Trenching, excavating, underground pipe installation - Fenced area
Noise: Medium level, occasional jackhammering
Closures: None
   